Defence Ministry Fixes TEJAS MK-1A Delivery Timeline For 97-Aircraft Order
The delivery schedule for the Indian Air Force’s second major order of 97 Light Combat Aircraft TEJAS MK-1A fighters has now been firmly defined, The Week reported.A defence ministry document confirms that deliveries will commence in September 2027 and conclude by September 2033. This provides a clear timeline for the induction of the aircraft into service.Hindustan Aeronautics Limited signed the
The delivery schedule for the Indian Air Force’s second major order of 97 Light Combat Aircraft TEJAS MK-1A fighters has now been firmly defined, The Week reported.A defence ministry document confirms that deliveries will commence in September 2027 and conclude by September 2033. This provides a clear timeline for the induction of the aircraft into service.Hindustan Aeronautics Limited signed the